The loading continues without issues. CPROP reports that they would like to perform an additional suite of tests before giving a near-term status of the LLCO system.
All the LLCO system test have been completed. So far the system appears good.
There will be an automatic cycling of the sensors once stable replenish is reached and only then can success be decalred by the launch team in Firing Room 4 of the Launch Control Center.
MILA antennas is now being aligned with 39A. For now they will remain in low power mode. Shortly before launch they'll switch to high power for final checks.
ECO sensor cycle test is now underway.
Final Inspection Team has arrived at the pad to inspect the vehicle for any ice or frost build-ups following tanking.
Orbiter Closeout Crew is also at the pad going up to 195 ft level of the FSS where the Orbiter Access Arm and the White Room is located.
The Final Inspection Team is now on the MLP Level 0 deck conducting the final phase of their inspections. They will then depart the pad and head for the LCC where they will brief Launch Director Doug Lyons on their findings.