Problem Apollo 9 CSM/LV Speraration

sterny70

New member
Joined
Jun 7, 2020
Messages
3
Reaction score
0
Points
1
Build 2254

I follow the PA checklist at MET 2:47 pushing the CSM/LV SEP Pushbutton and nothing happens
No Separation at all.
I followed the PAMFD Checklist to the letter but still no action.
SEP works fine for the other missions.

Sterny
 

rcflyinghokie

LM Junky
Addon Developer
Joined
Jun 4, 2016
Messages
616
Reaction score
331
Points
78
Location
Colorado
Build 2254

I follow the PA checklist at MET 2:47 pushing the CSM/LV SEP Pushbutton and nothing happens
No Separation at all.
I followed the PAMFD Checklist to the letter but still no action.
SEP works fine for the other missions.

Sterny
If you aren't getting a separation you have missed a step somewhere or perhaps aren't holding the button down (needs about a second.) Would you mind sending a scenario before sep so I can check your configuration?
 

sterny70

New member
Joined
Jun 7, 2020
Messages
3
Reaction score
0
Points
1
Hi
This is the step for SEP everything before was done according to the PAMFD Checklist.

Sterny
 

Attachments

  • T +00210 0001.scn
    140.9 KB · Views: 11

rcflyinghokie

LM Junky
Addon Developer
Joined
Jun 4, 2016
Messages
616
Reaction score
331
Points
78
Location
Colorado
Hi
This is the step for SEP everything before was done according to the PAMFD Checklist.

Sterny
Thanks! So it turns out we recently acquired Apollo 9's launch through TDE procedures, originally we assumed much of 8's were used. So in updating those I missed removing the opening of the pyro seq cbs on panel 250 from the EPS monitoring checklist. So this was a checklist error I will have a fix out for soon.

To fix your issue, close the pyro seq cbs on panel 250 :)
 

sterny70

New member
Joined
Jun 7, 2020
Messages
3
Reaction score
0
Points
1
Thank you so much.
now it works and i can continue.
 
Top