Default James Webb Space Telescope updates
by IronRain 02-18-2011, 12:16 PM

SpaceFlight Now: NASA official: JWST could still be on the ground in 2016

Quote:
Based on an ongoing budget impasse and the flat spending plan released by the White House this week, the troubled James Webb Space Telescope likely won't begin probing the universe until at least 2016, according to the mission's top manager.
Well, that ain't good news

What will be the effect of this on Hubble?

Last edited by IronRain; 04-14-2011 at 06:47 PM. Reason: Changed name and prefix
Reply With Quote
Views 52772 Comments 178
Total Comments 178

Comments

Old 02-18-2011, 01:30 PM   #2
hribek
Orbinaut
 
hribek's Avatar
Default

I'd say none. The Hubble will work for as long as it works, limited by battery life, gyroscope operability and so on.
hribek is offline   Reply With Quote
Old 04-14-2011, 06:46 PM   #3
IronRain
Moderator
 
IronRain's Avatar


Default

SpaceFlight Now: Budget pessimism may drive JWST launch date to 2018

Quote:
Struggling to match schedules with bleak funding realities, NASA and contractor officials say launch of the troubled James Webb Space Telescope could be delayed to 2018, four years later than the date NASA publicly pronounced last fall.
IronRain is offline   Reply With Quote
Old 04-15-2011, 12:08 AM   #4
Zachstar
Donator
 
Zachstar's Avatar

Default

More and more bad news for unmanned space exploration.
Zachstar is offline   Reply With Quote
Old 07-07-2011, 03:36 AM   #5
Krikkit
Orbinaut
 
Krikkit's Avatar
Default

Current 2012 budget calls for complete termination of the Webb telescope project

http://appropriations.house.gov/news...umentID=250023

It is times like these I wish I could curse on this forum
Krikkit is offline   Reply With Quote
Old 07-07-2011, 08:23 AM   #6
N_Molson
Addon Developer
 
N_Molson's Avatar

Default Spaceflight Now

House panel proposes killing Hubble telescope successor
BY STEPHEN CLARK
SPACEFLIGHT NOW

Posted: July 6, 2011



Legislators seeking to rein in government spending have put the troubled James Webb Space Telescope up for cancellation, saying the troubled successor to NASA's Hubble observatory is haunted by poor management and out-of-control costs.


Artist's concept of the James Webb Space Telescope. Credit: NASA/ESA

The next-generation space telescope is mired in a budgetary black hole. With an estimated cost of $6.5 billion and a cascade of delays, the flagship space mission could still be on the ground in 2018, NASA officials told Congress in April.

Managers privately said launch of JWST could slip even later due to federal spending cutbacks. President Obama's 2012 budget proposal called for flat spending on JWST at $375 million annually over the next five years.

Developed as the replacement for the Hubble Space Telescope, JWST is a joint project between NASA and the European Space Agency. With a 21.3-foot-diameter primary mirror, the telescope is designed to peer back in time almost to the Big Bang, giving astronomers a glimpse of infant galaxies as the universe cooled after its formation.

The proposal to terminate JWST came from the House Appropriations Committee's panel overseeing NASA. The committee released their 2012 spending bill Wednesday, calling for more than $1.6 billion in cuts to NASA's budget from this year's levels.

The Republican-led House subcommittee suggested a $16.8 billion NASA budget for fiscal year 2012, which begins in October. That's $1.9 billion less than the White House proposed in February.

"The bill also terminates funding for the James Webb Space Telescope, which is billions of dollars over budget and plagued by poor management," lawmakers said in a press release.

The Senate and the White House, which include JWST supporters, will weigh in on the federal budget before it becomes law. The budget must also pass the full House of Representatives.

NASA officials have repeatedly told Congress, researchers and journalists that JWST's exorbitant cost is prohibiting the agency from conducting other astrophysics missions. JWST's budget problems will likely keep NASA from launching a gravitational wave detector named LISA or the International X-ray Observatory until the 2020s.

In a report on NASA's JWST project management practices, an independent review panel said in November that the James Webb telescope needed an extra $500 million over the next two years to have a chance of launching by the end of 2015.

The additional funding never materialized, prompting NASA Administrator Charles Bolden to tell a Senate committee in April that a realistic estimate of JWST's launch date could be as late as 2018.

Before the independent review's release in November, NASA officially forecasted JWST would blast off in 2014. In the months since the panel issued its findings, NASA managers' unofficial statements have moved JWST's launch forecast four years later.


Six of JWST's 18 primary mirror segments have completed cryogenic testing. Credit: NASA

The report blamed mismanagement and poor budget discipline for the project's rising costs, leading JWST's cost billions of dollars beyond NASA's expectations. It pegged the mission's expected cost at $6.5 billion.

NASA has finished its own internal analysis of JWST's cost and schedule, according to Dwayne Brown, an agency spokesperson.

"This required a detailed analysis of all the work that remains to be done including all hardware components as well as a revised integration and test program," Brown told Spaceflight Now. "This has been completed and the new plan is undergoing independent review within the agency and by an outside team of experts to ensure adequate levels of both cost and schedule reserves in the appropriate years to successfully complete JWST development."

According to Brown, the new cost and schedule baseline will help inform the Obama administration's next federal budget request to be issued in February 2012. NASA's own budget and launch date projections will not be released until the internal reviews are complete, Brown said.

The independent review team concluded JWST was making steady technical progress despite the budget issues. About three-fourths of the telescope's hardware is already in production, according to Northrop Grumman Corp., JWST's prime contractor.

NASA announced last week that all of the telescope's mirrors completed polishing, and most of the beryllium mirror segments have been coated with a thin film of gold to efficently reflect infrared light. The mirror segments are also now undergoing cryogenic tests in a super-cold chamber at the Marshall Space Flight Center in Hunstville, Ala.

Scientists are also finishing work on JWST's four research instruments designed to peer deep into the cosmos and unravel how the infant universe formed and evolved.

But much more construction and testing remain, especially on the chassis that will contain JWST's science instruments and on the spacecraft itself.

---------- Post added at 08:23 AM ---------- Previous post was at 08:17 AM ----------

Now all those priceless "beryllium polished mirror segments" are probably going to end in a warehouse...

It looks like that science and fundamental research is considered as useless...
N_Molson is offline   Reply With Quote
Old 07-07-2011, 09:00 AM   #7
Richy
VTOL craft Pilot
 
Richy's Avatar
Default

Oh come on man! Why they cancel nearly every effort to space exploration? Just cancel the whole space programm, then there are no more budget exceedings in space research.
Richy is offline   Reply With Quote
Old 07-07-2011, 09:18 AM   #8
Keatah
Orbinaut
Default

Quote:
Originally Posted by hribek View Post
 I'd say none. The Hubble will work for as long as it works, limited by battery life, gyroscope operability and so on.
Actually, it will have quite an effect! Scientists and the technicians they boss around will realize how important HST is and treat it with the utmost care. Battery usage scheduling, magnetorquer and gyro operations will be scheduled and programmed to yield maximum life. More so now that JWST is just a paper spacecraft.

If money was so tight, why all of a sudden now?!? Why not catch the problem years ago? This is very typical. Politics and economics are not compatible with space exploration.

Last edited by Keatah; 07-07-2011 at 09:23 AM.
Keatah is offline   Reply With Quote
Thanked by:
Old 07-07-2011, 09:32 AM   #9
Artlav
Aperiodic traveller
 
Artlav's Avatar

Default

Maybe NASA can be financed commercially?
There got to be a few billionaires who care about research.

Or maybe Russia can finance the project, or provide launch vehicles and workforce for ~free.

There are ways, i suppose, to get it off the ground, but it's as if nobody cares enough to seek one.
Artlav is offline   Reply With Quote
Thanked by:
Old 07-07-2011, 10:24 AM   #10
Jarvitš
Orbinaut
Default

Sad news for science. I hope they manage to get it founded.
Jarvitš is offline   Reply With Quote
Old 07-07-2011, 11:07 AM   #11
agentgonzo
Grounded since '09
 
agentgonzo's Avatar
Default

I didn't even realise that the funding was under threat. When did this sneak up?
agentgonzo is offline   Reply With Quote
Old 07-07-2011, 12:12 PM   #12
ky
Director of Manned Spaceflight
 
ky's Avatar
Default

I know right.The one reason I hate America: Politicians and money.
ky is offline   Reply With Quote
Thanked by:
Old 07-07-2011, 12:49 PM   #13
SiberianTiger
News Sifter
 
SiberianTiger's Avatar

Default

Quote:
Originally Posted by Artlav View Post
 Or maybe Russia can finance the project, or provide launch vehicles and workforce for ~free.
Stepping aside from the question how come you get something for free in Russia, there's no Russian LV able to haul over 6000 kg into L2.
SiberianTiger is offline   Reply With Quote
Thanked by:
Old 07-07-2011, 12:54 PM   #14
Fabri91
Donator
 
Fabri91's Avatar
Default

I seriously hope this budget proposal gets revised, it seems more and more of a sport to kill projects once they have progressed a fair bit.
Fabri91 is offline   Reply With Quote
Thanked by:
Old 07-07-2011, 08:28 PM   #15
Notebook
Donator
 
Notebook's Avatar


Default

BBC article:

http://www.bbc.co.uk/news/science-environment-14073222

N.
Notebook is offline   Reply With Quote
Reply

  Orbiter-Forum > Far Side of the Moon > Spaceflight News


Thread Tools

Posting Rules
BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
Forum Jump


All times are GMT. The time now is 02:11 AM.

Quick Links Need Help?


About Us | Rules & Guidelines | TOS Policy | Privacy Policy

Orbiter-Forum is hosted at Orbithangar.com
Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2019, vBulletin Solutions Inc.
Copyright ©2007 - 2017, Orbiter-Forum.com. All rights reserved.